SouthCourtSq Reduced

Section name

Construction Projects Weekly 411

Jefferson/Jackson Corridor Streetscape –

Jefferson/Jackson Corridor Streetscape –

03/08/16 update: This streetscapes type project is approximately 90% complete and the corridor enhancements include new sidewalks, new decorative lighting, and new driveway aprons.  Jackson Street section has now been completed, as well as all the side streets.  Several design additions/revisions, field conditions, DOT repair work, and inclement weather have delayed the project’s original completion date.  Construction is almost complete along both sides of Jefferson Street and the project is slated to be complete, weather permitting, by the end of March 2016.  

 02/08/16 update: This streetscapes type project is approximately 80% complete and the corridor enhancements include new sidewalks, new decorative lighting, and new driveway aprons.  Jackson Street section has now been completed, as well as the side streets at Posey and Wesley.  Several design additions/revisions, field conditions, and inclement weather have delayed the project’s original completion date.  Construction is about two thirds of the way complete along both sides of Jefferson Street and the project is slated to be complete, weather permitting, by the end of February 2016.  

 01/13/16 update: This streetscapes type project is approximately 75% complete and the corridor enhancements include new sidewalks, new decorative lighting, and new driveway aprons.  Jackson Street section has now been completed, as well as the side streets at Posey and Wesley.  Several design additions/revisions, field conditions, and inclement weather have delayed the project’s original completion date.  Construction is about half way complete along both sides of Jefferson Street and the project is slated to be complete, weather permitting, by the end of February 2016.